Authored by Kiasha Nagiah, Eric Geldenhuys and Alistair Verhoogt.

An unsuccessful bidder cannot rely on a pending tender review to obtain an urgent interdict to extend the fixed-term contract being replaced after it expires despite failing to secure the contract in the new tender process. A court will only interfere with a public entity’s procurement powers in exceptional circumstances.

A pending review does not extend a fixed-term contract

In Bidvest Protea Coin (Pty) Ltd v Dube Transport Corporation and Another, the claimant provided aviation security services at a cargo terminal under a lawfully awarded tender. As the tender approached its expiry on 30 September 2026, the claimant submitted a bid for the replacement contract. However, the claimant failed the compliance stage of the tender process and did not secure the new contract. 

Following an unsuccessful internal appeal, the claimant launched an urgent application to prevent the public entity from implementing the new tender award pending its review application. The public entity, however, undertook not to implement the new tender until the court determined the review. The claimant nevertheless asked the court to order the public entity to retain it, at the existing rates, until the review concluded.

The court found that the existing contract contained no provision giving the claimant an automatic right to an extension. The contract therefore ended on the agreed date. The claimant knew the contract would expire. Its disappointment at the contract ending could not establish a reasonable apprehension of irreparable and imminent harm. Nor could it justify preventing a public entity from deciding with whom it contracts. The pending review likewise did not entitle the claimant to remain on site or continue providing services indefinitely.

Separation of powers 

The court emphasised that section 217 of the Constitution and the Public Finance Management Act of 1999 (PFMA) binds organs of state. The PFMA seeks to promote transparency, accountability and the sound management of the revenue, expenditure, assets, and liabilities of the institutions to which it applies. The court questioned how extending the contract would assist the procurement process. 

The court held that, a court must apply the requirements for an interim interdict with caution when an applicant seeks an order restraining a public entity from exercising its statutory powers. A court must avoid undue interference with executive functions under the separation of powers doctrine. Granting the relief could impede the public entity's ability to perform its statutory duties and to implement its supply chain management policy, which governs the procurement of goods and services. Consequently, a court should grant these interdicts only in exceptional circumstances and where the applicant has established a compelling case for intervention.

The claimant sought an order that would effectively compel the public entity to continue accepting and paying for its services after the fixed-term contract expired. The court therefore found that the claimant could not rely on the pending review proceedings to justify continuing of a contractual relationship that had already ended by agreement between the parties.

Bidvest Protea Coin (Pty) Ltd v Dube Transport Corporation and Another (2026-199256)